Nutanix Prism Central pc.2024.3 End of Life
Support dates and upgrade guidance — rebuilt from live data.
Nutanix Prism Central pc.2024.3 is actively supported. It reaches end of life on 31 Dec 2026.
Support timeline
Official dates from the Nutanix Prism Central release process.
| Milestone | Date | Status |
|---|---|---|
| Initial release | 5 Dec 2024 | — |
| End of life (scheduled) | 31 Dec 2026 | in 144 days |
| Active support ended | 31 Mar 2026 | security fixes only after this |
| Latest release | pc.2024.3.1.14 · 24 Mar 2026 | current |
How much runway a newer branch buys
Moving to Nutanix Prism Central pc.7.6 extends security support by about 578 days.
| Branch | End of life | Days left | vs pc.2024.3 |
|---|---|---|---|
| Nutanix Prism Central pc.7.6 | 31 Jul 2028 | 722 | +578 days |
| Nutanix Prism Central pc.7.5 | 30 Nov 2027 | 478 | +334 days |
| Nutanix Prism Central pc.7.3 | 30 Jun 2027 | 325 | +181 days |
| Nutanix Prism Central pc.2024.3 | 31 Dec 2026 | 144 | this branch |
| Nutanix Prism Central pc.2024.2 | 31 Oct 2026 | 83 | -61 days |
Frequently asked questions
When does Nutanix Prism Central pc.2024.3 reach end of life?
Nutanix Prism Central pc.2024.3 reaches end of life on 31 Dec 2026 — 144 days from now. After that date it receives no security fixes.
Is Nutanix Prism Central pc.2024.3 still supported?
Yes. Nutanix Prism Central pc.2024.3 is currently maintained. Latest release: pc.2024.3.1.14, published 24 Mar 2026.
What happens when Nutanix Prism Central pc.2024.3 reaches end of life?
Security fixes stop. After 31 Dec 2026 this branch receives no further updates under standard support.
How long do I have to upgrade from Nutanix Prism Central pc.2024.3?
144 days. Moving to Nutanix Prism Central pc.7.6 instead buys roughly 578 more days of security support.